Pouring concrete for the floor of the baggage cellar
Approximately 430 cubic meters of concrete has been poured for the basement floor of the baggage cellar. The second half of the floor will be poured on June 4th (weather permitting). After the concrete has hardened, the formwork will be removed and the concrete walls will be poured. This is scheduled to start from July 7th. At the end of July, the construction workers will enjoy a well-deserved three-week vacation. Therefore, no work will be done on the construction site during that time. After the summer vacation, the construction workers will start laying the floor for the ground level.